The Adventure RESUMES

The project starts up again on 3/20 with the delivery of framing materials and setup.

03/20/02 - Day 72

03/21/02 - Day 73
More materials delivered.

03/22/02 - Day 74

Window rough openings topped off. Sill plates installed.

03/25/02 - Day 77

A layer on top of the sill plates.

03/26/02 - Day 78

03/27/02 - Day 79
Subfloor is in place and the walls are going up!

03/28/02 - Day 80

03/29/02 - Day 81

04/01/02 - Day 84
Began work on soffit detail. Snowed out.

04/08/02 - Day 91
Snow has melted. Back to the soffits!

04/09/02 - Day 92
The old tin roof looses some ground.

04/10/02 - Day 93
No time for pictures. Too busy catching rain water leaking in through yesterday's demolition. Also water in basement because backfill and grading are not finished. F-U-N!!!

04/11/02 - Day 94
Rain, rain, go away. Come again when everything is finished and we need new grass to grow.

04/12/02 - Day 95
Roof decking.

04/15/02 - Day 98
Bathroom framed.

Soffit sheathing completed.

04/16/02 - Day 99
Wing detail added.