The Adventure Continues

The first fifteen days of this project saw major changes in our humble backyard. We also got some painting done inside and the blinds and curtains hung in the living room. What will the next 15 bring? Stay tuned.

01/23/02 - Day 16
The damp-proofing process begins. Kristo learns that they can't use the spray-on material because the chemical will eat up the styrofoam forms... Good to know! The guys use "dimple board" instead.

01/24/02 - Day 17
Foundation added for the flair detail we're incorporating from the front of the house.

Flair detail.

01/28/02 - Day 21
Backfill and rough grade today. Soon we'll have access to our back door again!


01/29/02 - Day 22
Dumpster delivered. No work today.

01/30/02 - Day 23
East window well delivered. East window opening prepped for installation.

01/31/02 - Day 24
West window opening prepped for window well installation.

Next >>